Dear partners!
Astyk Trans JSC hereby informs that in October 2018 an analysis on wagons downtime under initial and final operations (under freight operations) as well as along the route showed that, for example, the average downtime during loading and unloading (with a downtime rate for export of 2 days, in domestic directions 1 day) reached:
- Aktau port transshipment export - 6.06 and 3.56 days respectively;
- Azerbaijan - __ and 7.89 days respectively;
- Georgia - 6.6 and 7.4 days respectively;
- Middle Asia - 4.87 and 3.11 days respectively;
- China - 7.61 and 8.39 days respectively;
- Afghanistan - __ and 4.83 days respectively;
- In domestic directions - 4.02 and 2.48 days respectively.
When recalculating the actual turnover in absolute figures, the Company lost over 50,000 wagon turnover days, which results in 2,200 carloads.
Thus, dear partners, the Company asks you to work out the issues of timely loading and unloading of wagons, stipulated by the terms of the Forwarding Contract.
Best regards,
Astyk Trans JSC.